Work has started on the stair stringers. The existing structure will stay in place to support the new wood steps. The first "step" in the process was to remove the existing steps.
Our adventure in Condo Living... buying and combining two condo units
Monday, February 28, 2011
Sunday, February 27, 2011
Friday, February 25, 2011
Lot's of Activity Today...
More work on shower tile and vanity granite installed.
![]() |
Master shower & Beckie's vanity |
![]() |
Master tub & Lee's vanity |
![]() |
Master Shower - opening will be window for natural light |
![]() |
Breakfast Bar - sink area |
Laundry Room - stacked washer/dryer goes on left |
![]() |
Breakfast Bar - frig area |
![]() |
Guest Shower |
![]() |
Powder Room |
Tuesday, February 22, 2011
Making Progress Every Day...
Tile work continues for the showers, the remaining vanity cabinets are in place, and the vent hood is installed.
![]() |
View from Kitchen into Living Room |
![]() |
Powder Room |
![]() |
Lee's Vanity |
![]() |
Beckie's Vanity |
Monday, February 21, 2011
Stairs...
The stair railings and steps are in the process of being built off-site. Here is Beckie getting a workout with one of the sample steps.
Sunday, February 13, 2011
Friday, February 11, 2011
Monday, February 7, 2011
Ready, Set, Go Cabinets...
Here's some photos of work-in-progress for the Wall Bed install in the Guest Bedroom (downstairs) and existing cabinet re-install in the Kitchenette and Laundry (upstairs).
Sunday, February 6, 2011
Starting Cabinets...
Here's some photos of getting ready to re-install the existing cabinets in the Kitchenette (upstairs) and in the install in-progress of the first vanity in the Guest Bath (downstairs).