Sunday, December 26, 2010

Ready to Rock...

Last week we finally got the "okay to rock" with the final framing green tag.  Unfortunately, it was after a slight delay to correct a "red tag" on the dryer vent pipe material.  It was fixed within hours; however, it required calling-back both the Mechnical and Framing inspectors which took most of a week.  Some work was able to continue, but we were only able to really start (sheet)rockin' on Dec 22nd.  Sheetrock rough-in should be done by Dec 29th.  The stained concrete will be done next before continuing with tape, bed, float, and trim the following week.